AMERICAN ENVIRONMENTAL & CONSTRUCTION SERVICES, INC.

(AECS)


Project Experience - UST Removal

Client:             US Postal Service        

Location:        US Postal Service Facilities in Georgia, Alabama,

                        Florida, and Mississippi

Project Cost:      $ 640,000                           

                                                                                                                        Removing a 12,000g UST

Project Description                                                                                                       

AECS has been awarded multiple contracts by the US Postal Service Facilities Service Office in Atlanta, GA to remove underground storage tanks (UST), fueling facilities, contaminated soil, and all associated electrical and plumbing fixtures and other appurtenances associated with these facilities at various facilities located in Georgia, Alabama, and Florida.  In many instances AECS replaced the USTs with aboveground storage tanks (AST). 

Specific Projects:

USPS Waycross, GA – VMF, UST Removal/AST Installation

AECS was contracted by the US Postal Service to remove underground fuel and oil storage tanks and install an above-ground waste oil storage tank at its Waycross, GA Vehicle Maintenance Facility.   

The project involved the removal and disposal of brine, free product and sludge; the demolition and disposal of a concrete covering; the excavation and removal of one 2,000-gal and two 1,000-gal underground fuel storage tanks and the closure in place of one 300-gal underground waste oil storage tank.

When the tanks had been removed, the soil was sampled and analyzed, and it was discovered that they had leaked and contaminated both the soil and ground water. It was then necessary to excavate, load, transport and dispose of over 100 tons of contaminated soil and over 1,000 gal of contaminated groundwater.

AECS installed a 280-gal aboveground waste oil storage tank; backfilled the excavations; and restored the site with placement of asphalt and seeding, fertilizing, and mulching impacted grass areas.

 

USPS Norcross, GA – UST and Fueling Facility Removal

AECS was contracted by the US Postal Service to demolish and remove its fueling facility at its Norcross, GA – Peachtree Corners Station. 

The project involved the demolition, removal, and disposal of a fueling island with associated canopy, dispensers, and appurtenances; the removal and disposal of brine, free product and sludge; sawcutting, removal and disposal of the concrete covering; excavation, removal, transportation and disposal of two 12,000-gal steel-walled underground fuel storage tanks and associated piping; installation of new oil and air pumps; and backfill, compaction, and restoration of the excavation, including resurfacing with asphalt. 

During the project, the Post Office and project site were hit by a tornado and the contract was modified to provide for restoration of the Post Office, including the cutting, removal, and cleanup of approximately 100 downed and partially downed trees and several hundred cubic yards of storm debris.

 

USPS Montgomery, AL – UST Removal and AST Installation

AECS was contracted by the US Postal Service to remove three 12,000-gal underground fuel storage tanks, two 1,000-gal underground oil storage tanks, and one 2,500-gal underground waste oil storage tank and to install two aboveground oil storage tanks.

The project involved sawcutting and removal of the concrete covering over the three 12,000-gal USTs; removal and disposal of brine, free product and sludge; removal, demolition, and disposal of the tanks; backfilling of the excavation; and restoration including concrete replacement.  The three oil storage tanks were closed in place and new concrete placed.  Pads were constructed and piping rerouted for the new ASTs, which were then installed.

 

USPS Decatur, AL- UST and Fueling Facility Removal  

AECS was contracted by the US Postal Service to demolish and remove its fueling facility at its Decatur, AL main postal facility.

The project involved the demolition, removal and disposal of a fueling island with associated dispenser and appurtenances; removal of brine, free product and sludge; sawcutting, removal and disposal of the concrete covering; removal and disposal of one 4,000-gal UST with piping and monitoring wells; backfill, compaction, and replacement of the concrete covering; cleaning and closure in place with flowable fill of one 6,000-gal UST; and replacement of its concrete covering.

 

USPS Florence, AL- UST and Fueling Facility Removal  

AECS was contracted by the US Postal Service to demolish and remove its fueling facility at its Florence, AL main postal facility.

The project involved the demolition, removal and disposal of a fueling island with associated dispenser and appurtenances; removal of brine, free product, and sludge; sawcutting, removal and disposal of the concrete covering; excavation, removal, transportation and disposal of one 12,000-gal UST with all associated piping, appurtenances, and monitoring wells; backfill of the excavation, compaction, and replacement of the concrete covering.

 

USPS Columbus, GA – UST and Fueling Facility Removal / AST Installation  

AECS was contracted by the US Postal Service to demolish and remove its fueling facility at the Columbus, GA Vehicle Maintenance Facility and to install a replacement aboveground storage tank.

The project involved the demolition, removal and disposal of a concrete fueling island with canopy, dispensers and associated piping and appurtenances; removal and disposal of brine, free product, and sludge; sawcutting, removal and disposal of concrete covering; excavation, removal, transportation and disposal of one 12,000-gal and two 1,000-gal USTs with all piping, controls, and appurtenances; backfilling, compacting, and resurfacing the excavations with asphalt; and installation of a Lube Cube AST with pumps, piping, and controls.

 

USPS Roswell, GA – Contaminated Soil Removal

AECS was contracted by Kiber Environmental on behalf of the US Postal Service to excavate, load, transport and dispose of 700 tons of petroleum contaminated soil from the USPS Roswell Main Post Office facility in Roswell, GA.  The project consisted of excavating, loading, transporting, and disposing of the contaminated soil and backfilling the excavation with 700 tons of #57 stone.

 

USPS Savannah, GA – UST Closure/AST Installation

AECS was contracted by the US Postal Service to close in place one 12,000-gal, one 4,000-gal, one 2,500-gal, and one 600-gal UST and to install one 650-gal split compartment AST at its Savannah, GA Vehicle Maintenance Facility.

The project consisted of sawcutting and removal of asphalt and concrete coverings, curbs, and a concrete fuel island; removal and disposal of free product and sludge; demolition and removal of the fueling facility, including canopy, island, dispensers, piping, and appurtenances; cleaning, drying, and closure in place of the four USTs using inert foam; construction of a concrete pad and installation of the AST; backfill and compaction of soil; and replacement of the removed asphalt and concrete with new concrete.

 

USPS Savannah, GA – UST Closure

  AECS was contracted by the US Postal Service to excavate, remove, transport and dispose of one 12,000-gal UST (later changed to a closure in place) at its Savannah, GA Oglethorpe Station facility. 

The project involved demolition, removal, loading, transportation and disposal of the concrete covering; removal and disposal of brine, free product and sludge; cleaning, drying, and closure in place with foam of the 12,000-gal UST; and replacement and paving of the excavated area with asphalt.

 

USPS Panama City, FL – UST and Fueling Facility Removal

AECS was contracted by the US Postal Service to demolish its fueling facility and to excavate, load, transport and dispose of the fueling facility and a 12,000-gal UST (later changed to a closure in place). 

The project involved demolition, loading, transportation and disposal of the fueling facility including, canopy, dispenser, island, piping and appurtenances; sawcutting and removal of the concrete slab covering the UST; removal and disposal of brine, free product, and sludge; cleaning and closure in place using flowable fill of the 12,000-gal UST; backfilling, compaction, and replacement of the removed concrete with new concrete.

 

USPS Gainesville, FL – UST and Fueling Facility Removal / AST Installation

AECS was contracted by the US Postal Service to demolish its fueling facility and to excavate, load, transport and dispose of two 12,000-gal, one 550-gal, and three 500-gal USTs (later changed to closure in place) at its Gainesville, FL Vehicle Maintenance Facility and its General Maintenance Facility and to install one 500-gal AST. 

The project involved sawcutting, removal, and disposal of 3,000 sq ft of concrete and asphalt covering over the tanks; removal and disposal of free product, brine, and sludge from the tanks; cleaning and closure in place of the six USTs with inert foam; demolition, removal and disposal of the fueling facility including dispensers, piping and appurtenances; modification of a sand separator into a temporary catch basin; installation of a high level alarm system in the basin; backfill and compaction of the excavations; replacement of the removed concrete with new concrete; and installation of new 500-gal split double containment AST.

 

USPS Jackson, MS – UST & OWS Removal/Aboveground OWS Installation

AECS was contracted by the US Postal Service to clean and remove the underground oil/water separator, to close in place an underground oil storage tank, and to install an aboveground oil/water separator at its Jackson, MS vehicle maintenance facility.  Significant contamination was found, and eventually the project involved removal, transportation and disposal of residual material in the UST and OWS; saw cutting of concrete above the UST and the OWS and along the drainage lines to the sewer system; removal of the UST and OWS; probing with a Geoprobe and investigating by excavation to trace and  determine the extent of contamination; removal, stockpiling, transportation and disposal of contaminated debris and soil; removal and replacement of the sewer pipeline; installation of a new 12’ underground sludge tank; backfilling with pea gravel; and restoring the surface with new concrete.  An aboveground Oil/Water Separator was installed, including all plumbing and electrical.

 

 

Projects            Home            Contact Us